What NRM2 is used for
NRM2 provides a recognised structure and measurement rules for detailed building work. It helps quantities, descriptions and units follow a consistent logic so tenderers understand what is measured and how the work is grouped. For contractors, its value is practical: a structured Bill of Quantities can make subcontract enquiries, tender comparison and later commercial review clearer. Using NRM2 principles does not remove the need to read the drawings, specification, preambles and contract documents together.
Measurement follows the construction
The work is broken into measurable components rather than hidden in broad elemental allowances. Excavation is distinguished from disposal and filling; concrete from formwork and reinforcement; masonry from DPCs, insulation, lintels and associated components. Openings, finishes, services and external works use the units suited to the item. This structure lets an estimator attach labour, materials, plant or specialist costs to the work that actually creates them.
Descriptions still carry responsibility
A quantity alone is not a complete scope. Descriptions should identify the material, thickness, location, performance or installation basis where the information defines it. Preambles and specification clauses may add workmanship, testing, samples or attendance obligations that are not apparent from the dimension. Contractors should also check whether temporary work, protection, waste, fixings and sundries are included in the rate or measured separately under the stated rules.
Preliminaries and uncertain work
Management, welfare, temporary services, security, access and other project-wide resources are normally considered separately from measured building work. Undefined design or ground risk should not be converted into false precision. A provisional sum, prime cost allowance, qualification or request for information may be more honest than measuring an item the documents do not define. The basis must remain visible to everyone reviewing the tender.
Using an NRM2-based BoQ commercially
Treat the BoQ as a pricing and control document, not a substitute for the full tender pack. Reconcile its quantities and descriptions against drawings, schedules and revisions. Identify client-supplied goods, design responsibilities and package interfaces. Then apply rates that reflect your actual labour outputs, purchasing terms, plant, subcontract quotations and project conditions. The final tender should state departures, assumptions and exclusions rather than relying on the BoQ to communicate them implicitly.